BuzzerBeater Forums

Bugs, bugs, bugs > Arena expansion delay 7+ days

Arena expansion delay 7+ days

Set priority
Show messages by
From: NS
This Post:
00
115207.1
Date: 10/11/2009 22:12:19
Overall Posts Rated:
88
I know rules state arena expansion dates are not exact. However, I began construction on the 29th with an expected time of 13 days. It is now the 11th and it states I have 8 days remaining. Has anyone else had this many days (7 or more) of difference between expected and actual completion?
Is this right or bug?

From: bumbumalot

To: NS
This Post:
00
115207.2 in reply to 115207.1
Date: 10/12/2009 11:13:15
Overall Posts Rated:
00
its right. its an estimation not a will be complete date

From: NS
This Post:
00
115207.3 in reply to 115207.2
Date: 10/12/2009 13:02:04
Overall Posts Rated:
88
Understandable, but another day has gone by and its still says 8 days. So from a 13 day estimate it will take at least 21 days?! I have done similar work to my stadium twice before (1000 Bleachers, 500 Lower Tier) and is usually complete by 12-14 days, not 21. I know its an estimate, just seems way off in this case.

From: Newton07

To: NS
This Post:
00
115207.4 in reply to 115207.3
Date: 10/12/2009 13:34:42
Overall Posts Rated:
3535
strictly speaking is not a bug, but I agree with you that is silly to have a system in which the vast majority of the times there is a delay, and quite often a large delay. I would prefer a longer estimation, with a smaller chance (than now) to have a delay and a bigger chance (than now) to have works finished ahead of time.

For me this time it was supposed to be 11 days... and after 14 days there are still 2 left.

This Post:
00
115207.5 in reply to 115207.4
Date: 10/12/2009 15:46:27
1986 Celtics
IV.10
Overall Posts Rated:
88
construction projects never finish before schedule, sometimes they finish on schedule, so on average the estimate is always an underestimate of the amount of time. We think this is a very realistic system to implement delays. You hope each day that nothing goes wrong, but sometimes something does go wrong.. materials don't arrive etc. I understand that you might argue for a smaller variance in how long it takes, basically that you don't want as many delays, but I think the way we report the estimated time makes real world sense. I wouldn't want an estimate that would sometimes be over and sometimes be under, as that's not how construction goes. In reality its not important whether the estimate is over or under, in fact you know that its an underestimate and smart managers will come to realize this and make their plans accordingly, instead of wishing hopefully that things would turn out exactly as the estimate they were given. We think this is a good mark of a smart manager, one who anticipates the worst case scenario and manages his team for that.

I agree it would be easier to do it otherwise, it would be easier to not have any delays at all.. in fact it would be easiest for managers if they didn't have to wait for construction to happen at all... but we built this game to be a management challenge, and we do think this particular aspect leads people to have to make interesting decisions and react to the unexpected.

Last edited by BB-Forrest at 10/12/2009 15:47:44

This Post:
00
115207.6 in reply to 115207.5
Date: 10/12/2009 16:48:55
Overall Posts Rated:
3535
at least it does not work like in italy, where also the costs can turn out to be much higher than the estimated ones :D

From: Switch
This Post:
00
115207.7 in reply to 115207.6
Date: 11/11/2009 06:31:24
Overall Posts Rated:
33
i like it, it makes the game feel more realistic :)

This Post:
00
115207.8 in reply to 115207.6
Date: 11/15/2009 11:41:05
Overall Posts Rated:
457457
That is not only Italy, Paisano. My house was not only late but also over budget.

Last edited by somdetsfinest at 11/15/2009 11:42:22

Once I scored a basket that still makes me laugh.